How we work
One team, one execution flow — from study to stable output
Six stages, each closed by a gate you sign off. You always know what has been agreed, what comes next and who is accountable.
Six stages
The Mecwerx execution flow
Study
Site visit, product and volume review, constraints, risks and a budget envelope.
- You receive
- Scope note, indicative budget and schedule
- Gate
- Go / no-go on concept and budget
Engineer
Process design, line balance, layouts, 3D design, electrical and controls design, utilities data and design reviews.
- You receive
- Layouts, 3D models, specifications, utilities schedule
- Gate
- Design freeze — your sign-off
Build
Manufacture, assembly, wiring and programming with stage inspections.
- You receive
- Progress reports and inspection records
- Gate
- Factory acceptance test (FAT) with your parts
Install
Site-readiness check, dispatch, erection, alignment and utilities hook-up.
- You receive
- Installation plan and readiness checklist
- Gate
- Mechanical and electrical completion
Commission
I/O and sequence checks, safety functions, trials, cycle-time and quality proving.
- You receive
- Commissioning protocol and results
- Gate
- Site acceptance test (SAT) against agreed criteria
Stabilise & support
Ramp-up support, training, punch-list closure, handover and AMC options.
- You receive
- Handover dossier, training records, support plan
- Gate
- Handover sign-off
Governance
How projects stay on track
- One project manager as your single point of contact
- Weekly progress report with schedule and open points
- Design reviews at concept stage and before freeze
- Change requests documented with cost and time impact before execution
- Stage inspections during build
- FAT and SAT against written protocols
- Punch lists tracked to closure with owners and dates
- Escalation path to leadership at info@dryshades.com
Engagement models
Buy it the way that suits your project
Turnkey (lump sum)
Complete scope against a frozen specification — design, build, install, commission — with milestone payments.
Design & build
We engineer and build the equipment; you handle civil and utilities using our data.
Engineering study first
A paid study — layout, line balance, concept and budget — before you commit to the build.
Installation & commissioning
Site execution and ramp-up for equipment built by us or by others.
AMC & post-handover support
Preventive maintenance, breakdown support, spares and modifications.
Upgrade & retrofit
Capacity, automation, safety and traceability upgrades to existing lines and machines.
FAQ
Frequently asked questions
How are payments structured?
Typically as milestones linked to order, design freeze, FAT, delivery and SAT. The exact split is agreed per project and written into the contract.
What happens if the scope changes mid-project?
Changes are raised as change requests with their cost and schedule impact documented and approved before any work on them starts.
Who is our point of contact?
One project manager from study to handover, with a clear escalation path to leadership.
Is the equipment covered by warranty?
Yes. Warranty terms are defined in each contract, with post-handover support and AMC options beyond the warranty period.
Start a project
Hand over your production challenge.
Tell us what the line has to produce, where, and by when. We will come back with a scoped approach, a realistic timeline and the questions that matter — usually after a site visit or a drawing review.